Modern Government Maternity Hospital (MGMH) — Reproductive Medicine & Examination Block Rehabilitation
VS-004Completed

Reproductive Medicine & Examination Block Rehabilitation

Modern Government Maternity Hospital (MGMH) · Hyderabad, Telangana

Executive Summary

Specialized reproductive medicine facilities required sanitation upgrades.

Impact Highlights

11 units

Washroom units documented

Before-and-after units documented in the VS-004 project profile

Scope of Work

Lining washrooms, IVF, DSRC, reproductive medicine and examination areas.

Major Works Executed

Complete washroom rehabilitation and plumbing upgrades.

Before & After Transformation

IVF Old OP Washroom – before renovationBEFORE
IVF Old OP Washroom – after renovationAFTER

IVF Old OP Washroom

We have Dismatled the flooring, Installed the new waste pipe connection, laid new tiles and installed the

Reproductive Medicine (I-58) – before renovationBEFORE
Reproductive Medicine (I-58) – after renovationAFTER

Reproductive Medicine (I-58)

We have Dismatled the flooring, Installed the waste pipe connection, laid new tiles and installed the washbasin

Examination hall Right (III - 30) – before renovationBEFORE
Examination hall Right (III - 30) – after renovationAFTER

Examination hall Right (III - 30)

We have installed the taps and jaali

Examination hall Right (III - 29) – before renovationBEFORE
Examination hall Right (III - 29) – after renovationAFTER

Examination hall Right (III - 29)

We have installed the taps and jaali

Examination hall Right (III - 21) – before renovationBEFORE
Examination hall Right (III - 21) – after renovationAFTER

Examination hall Right (III - 21)

We have installed the taps, Flush tank, Connection pipe and jaali

Examination hall Right (III - 22) – before renovationBEFORE
Examination hall Right (III - 22) – after renovationAFTER

Examination hall Right (III - 22)

We have installed the taps, Connection pipe and jaali

Examination hall Right (III - 23) – before renovationBEFORE
Examination hall Right (III - 23) – after renovationAFTER

Examination hall Right (III - 23)

We have installed the taps, Seat cover, Connection pipe and jaali

Examination hall Right Corridor – before renovationBEFORE
Examination hall Right Corridor – after renovationAFTER

Examination hall Right Corridor

We have installed the washbasin taps, connection pipe, angle cocks and waste pipes

Examination room (II - 28) – before renovationBEFORE
Examination room (II - 28) – after renovationAFTER

Examination room (II - 28)

We have installed the Flush tank and water tap

Nurse changing room – before renovationBEFORE
Nurse changing room – after renovationAFTER

Nurse changing room

We have installed the tap

Electric room – before renovationBEFORE
Electric room – after renovationAFTER

Electric room

We have installed the washbasin tap, water tap, flushtank, seat cover

Project Budget

ComponentAmount
Blockage Rehabilitation₹3,20,000
Repair Works₹1,22,846
Total Project Budget₹4,42,846

Expected Impact

Cleaner and safer environment for patients and staff.

Project Gallery

Hospital washroom renovation workHospital washroom renovation workHospital washroom renovation workHospital washroom renovation workHospital washroom renovation workHospital washroom renovation workHospital washroom renovation workHospital washroom renovation workHospital washroom renovation workHospital washroom renovation workHospital washroom renovation workHospital washroom renovation work

Lining right (I - 8); Lining right (I - 9)

Partners

Vikasa Tarangini (India), VT Seva (USA), MGMH Hospital Administration